NEW QUESTION 38
Which one of the following relationship types means that the end of one operation is linked to the start of the next operation?
- A. Finish - Start
- B. Start - Finish
- C. Start - Start
- D. Finish - Finish
Answer: A
NEW QUESTION 39
You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time - key date. The orders should be called 3 months before the planned date. How can you set up the maintenance plan? Note: There are 2 correct Answers to this question.
- A. Set the call horizon to 90 days.
- B. Set the call horizon to 25%.
- C. Set the call horizon to 75%.
- D. Set the offset to 3 months.
Answer: B
NEW QUESTION 40
You want to schedule a performance-based maintenance plan. Which parameters are mandatory? Note: There are 2 correct answers to this question.
- A. Estimated annual performance
- B. Shift factors
- C. Start counter reading
- D. Scheduling period
Answer: A,C
NEW QUESTION 41
When the planner checks the capacity load of work center, which data of the order is used? choose 2 answers
- A. basic start
- B. duration of the activity
- C. scheduled start
- D. amount of work
Answer: B,D
NEW QUESTION 42
A billing document can be createdfrom what two types of documents?
- A. Quotation
- B. Sales order
- C. Rebate list
- D. Delivery
- E. Inquiry
Answer: B,D
NEW QUESTION 43
Which objects can a personnel number be assigned to directly?Note: There are 2 correct answers to this question.
- A. Planner group
- B. Business partner
- C. Equipment
- D. Work center
Answer: B,C
NEW QUESTION 44
Which functions are available in the Resource Scheduling for Maintenance Planners app? Note: There are 2 correct Answers to this question.
- A. Schedule and dispatch maintenance operations by shifts.
- B. Print job papers from a maintenance order.
- C. Monitor maintenance order operations due in the next 4 weeks.
- D. Cancel dispatched maintenance order operations.
Answer: C,D
NEW QUESTION 45
How does the work center influence cost calculation in the maintenance order? Note: There are 2 correct Answers to this question.
- A. Via activity type and hourly rate
- B. Via organizational unit and personal hourly rate
- C. Via business partner and hourly price
- D. Via cost center and activity type
Answer: A,D
NEW QUESTION 46
What happens if you change the primary key of a functional location?
- A. The functional location is immediately assigned to a new superior functional location when the new label is entered.
- B. The user must decide whether the functional location is assigned to a new superior functional location.
- C. The user must define a new labelling system for the new primary key.
- D. Changing the superior functional location via alternative labeling is not possible.
Answer: A
NEW QUESTION 47
The maintenance engineer creates a singel cycle plan with the following parameters:
* the call object is maintenance order
* the indicator or seprate completion of maintenance call date is NOT set
* the indicator for completion requirement is NOT activated
* both shift factors are set to 100% .
Which date is relevant for the calculation for further planned dates for all objects? choose 1 answer
- A. technical completion date of the maintenance order
- B. completion date of maintenance plan
- C. planned date of the next call number
- D. basic finish date of the maintenance order
Answer: C
NEW QUESTION 48
Which options do you have to allow the assingment of order operation to object list entries. choose 3 answer
- A. to all maintenance plans
- B. to all object list entries
- C. to all notification
- D. to all task list
- E. only to notifiaction created via maintenance plans
Answer: B,C,E
NEW QUESTION 49
Which of the following is true about SAP Work Manager?
- A. It is used in combinations with SAP ERP and S/4HANA
- B. It is availableonly on SAP Cloud Platform
- C. It is available in On Premise Edition and Cloud Edition
- D. It is used in combinations with S/4HANA
Answer: A,C
NEW QUESTION 50
What happens when you enter an invoice with reference to a purchase order?
- A. The system suggests data only from the goods receipt.
- B. The system suggests data only from the purchase order.
- C. The system suggests data from the purchase order and the goods receipt.
Answer: C
NEW QUESTION 51
Which statements are correct for standard processes in PM/PS cost control? Note: There are 2 correct Answers to this question.
- A. Maintenance order costs can be settled to a WBS element.
- B. Maintenance costs can be settled to a network operation.
- C. Budget can be assigned to a WBS element.
- D. Budget can be assigned to a maintenance plan.
Answer: A,C
NEW QUESTION 52
Which of the following are valid schedulingparameter in the multiple-counter plan? choose 2 answers
- A. start counter reading
- B. call horizon
- C. schedule period
- D. Or-link
Answer: C,D
NEW QUESTION 53
A piece of equipment cannot be linked to a material. Determine whether this statement is true or false.
- A. False
- B. True
Answer: A
NEW QUESTION 54
Which of the following BOMs we use to set up spare parts planning of functional locations
- A. Maintenance BOM
- B. Production BOM
- C. Costing BOM
- D. construction BOM
Answer: A
NEW QUESTION 55
Which operations are possible when you cancel the technical completion of a maintenance order? Note: There are 2 correct answers to this question.
- A. Change the estimated costs.
- B. Change the priority.
- C. Book a goods receipt.
- D. Cancel status Released.
Answer: B,C
NEW QUESTION 56
......